Tiling on brickwork
I am getting an en-suite bathroom built in a new extension to my brick veneer home. One wall of the new bathroom is a single brick ( with piers) wall of my existing garage. Part of the wall is to be tiled, as it is one side of the shower recess.
Space is very limited in the shower.
Can anyone help with suggestions for tiling that will keep the wall as thin as possible (to maximise space in the shower. Can I stick Villaboard directly to the bricks, or do I need batons? etc
Cheers
Mark
-
4th April 2008, 11:48 PM #2
Should be able to stick villaboard to bricks, construction adhesive will hold it.
....................................................................
-
5th April 2008, 06:29 AM #3
Hi Mark,
Don't want to rain on your parade, but whilst adhesive can be the go for untiled villaboard, James Hardie will not warrant it if tiled, unless batons are used. How far up the wall will the tile extend?
Here is a link to their full Villaboard installation manual. Just scroll down to the bottom and you can download the entire manual to your computer.
http://www.jameshardie.com.au/Produc...llationManual/
Cheers,
Bob
-
5th April 2008, 07:35 AM #4Member
- Join Date
- Feb 2008
- Location
- nsw
- Posts
- 73
common building practice for your situation is to cement render the brickwork which will be 5-7mm thick (so you get a flat, plumb and smooth substrate to tile to) then roll on ya waterproofing and glue yer tiles to that
-
5th April 2008, 12:53 PM #5New Member
- Join Date
- Mar 2008
- Location
- perth
- Posts
- 9
hi skyhook
there is a new pvc product available in the market that can do the job you require , added to the fact that you will not need to tile afterwards .
in your area i'm sure that a company called cozyhome stock it. if not click into the link
for more info . http://www.homeimprovementpages.com....essional/52621
-
5th April 2008, 11:30 PM #6Amateur D-I-Yer
- Join Date
- Mar 2008
- Location
- Byron Bay
- Posts
- 52
-
6th April 2008, 08:15 AM #7Amateur D-I-Yer
- Join Date
- Mar 2008
- Location
- Byron Bay
- Posts
- 52
-
7th April 2008, 09:56 PM #8Novice
- Join Date
- Mar 2008
- Location
- outer sydney
- Posts
- 21
render usually should be left for a period of 7 days, that is taking into consideration weather and thickness of render.
then you have to allow at least 2 days for waterproofing before tiling can take place
Similar Threads
-
Brickwork problems
By brettsyoung in forum BRICKWORKReplies: 3Last Post: 2nd March 2008, 06:59 PM -
Sealing Brickwork
By AlexJ66 in forum BRICKWORKReplies: 6Last Post: 15th September 2007, 12:17 PM -
extending brickwork
By scottyb in forum BRICKWORKReplies: 4Last Post: 20th August 2007, 10:12 PM -
Levelling Brickwork
By Clive McF in forum BRICKWORKReplies: 15Last Post: 17th April 2006, 10:37 PM -
Brickwork Query
By Hootsmon in forum BRICKWORKReplies: 7Last Post: 11th August 2005, 06:38 PM
Bookmarks