Help with stage one... time periods
hi guys
i would just like to know how long each of these steps will take on average for building a new house
Slab on Ground
-Site Set out
-Excavation
-Form Work
-Vapour Barrier
-Bar Chairs
-Pooring Concrete
-
4th April 2006, 05:38 PM #2
Turbo,
you could have all of that done in a few days if all went well.
Try getting a hold of the book "Australian Owner Builder" by Alan Staines.
It has all of this sort of info in there.Have a nice day - Cheers
-
4th April 2006, 10:31 PM #3Originally Posted by Wood Butcher
Cheers
Justine
-
4th April 2006, 10:57 PM #4Originally Posted by TuRb0
-Site Set out allow one day
-Excavation depends,
how big an excavator are you going to use?
How many trucks?
how far have you got to cart the excavated material?
little excavator, small truck = many trips to the dump/tip plus lots of time working through any hard stuff
big excavator, 2 or 3 big trucks = not long at all. A friend got ALL his excavation (about 1200 cu.m) done one Saturday morning using a largish Kato and two 14 tonne tippers and a very short haul
who is going to supervise the excavator operator, you?
-Form Work }
-Vapour Barrier } these all depend on the number of bodies used
-Bar Chairs }
-Pooring Concrete allow one day
-
4th April 2006, 10:57 PM #5
A professional team of 2 concretors will knock over most house slabs in less than a week.
Similar Threads
-
What is two years of your time worth?
By journeyman Mick in forum NOTHING AT ALL TO DO WITH RENOVATIONReplies: 26Last Post: 18th November 2004, 10:26 AM -
Daylight Saving Time
By silentC in forum POLLSReplies: 42Last Post: 22nd October 2004, 09:32 PM -
Performance appraisal time
By Pete in forum JOKESReplies: 0Last Post: 12th November 2001, 01:21 PM -
My First Time
By DonN in forum JOKESReplies: 2Last Post: 27th December 2000, 03:59 PM
Bookmarks