    Default Help with stage one... time periods

    hi guys
    i would just like to know how long each of these steps will take on average for building a new house

    Slab on Ground
    -Site Set out
    -Excavation
    -Form Work
    -Vapour Barrier
    -Bar Chairs
    -Pooring Concrete

  2. #2
    Join Date
    Oct 2001
    Location
    Warwick, QLD
    Age
    45
    Posts
    1,175

    Default

    Turbo,
    you could have all of that done in a few days if all went well.

    Try getting a hold of the book "Australian Owner Builder" by Alan Staines.
    It has all of this sort of info in there.
    Have a nice day - Cheers

  3. #3
    Join Date
    Jun 2005
    Location
    Melbourne
    Age
    51
    Posts
    119

    Default

    Quote Originally Posted by Wood Butcher
    you could have all of that done in a few days if all went well.
    When you've done your assessment - double everything (that goes for budget too!)
    Cheers
    Justine

  4. #4
    Join Date
    Feb 2003
    Location
    back in Alberta for a while
    Age
    69
    Posts
    1,133

    Default

    Quote Originally Posted by TuRb0
    hi guys
    i would just like to know how long each of these steps will take on average for building a new house
    Slab on Ground
    -Site Set out allow one day
    -Excavation depends,
    how big an excavator are you going to use?
    How many trucks?
    how far have you got to cart the excavated material?
    little excavator, small truck = many trips to the dump/tip plus lots of time working through any hard stuff
    big excavator, 2 or 3 big trucks = not long at all. A friend got ALL his excavation (about 1200 cu.m) done one Saturday morning using a largish Kato and two 14 tonne tippers and a very short haul
    who is going to supervise the excavator operator, you?

    -Form Work }
    -Vapour Barrier } these all depend on the number of bodies used
    -Bar Chairs }
    -Pooring Concrete allow one day

  5. #5
    Join Date
    Mar 2005
    Location
    Too close to Sydney
    Posts
    133

    Default

    A professional team of 2 concretors will knock over most house slabs in less than a week.

Similar Threads

  1. What is two years of your time worth?
    By journeyman Mick in forum NOTHING AT ALL TO DO WITH RENOVATION
    Replies: 26
    Last Post: 18th November 2004, 10:26 AM
  2. Daylight Saving Time
    By silentC in forum POLLS
    Replies: 42
    Last Post: 22nd October 2004, 09:32 PM
  3. Performance appraisal time
    By Pete in forum JOKES
    Replies: 0
    Last Post: 12th November 2001, 01:21 PM
  4. My First Time
    By DonN in forum JOKES
    Replies: 2
    Last Post: 27th December 2000, 03:59 PM

Tags for this Thread

Bookmarks

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •