    Question fixing acrylic bath into cradle

    I am installing an Englefield 'plastic' bath (acrylic, I guess) against a wall, and to save money I want to build the bath frame and install the bath myself. I called the technical helpline and they said the bath does not come with instructions for frame construction and offered no advice on this, but happened to mention that I should glue the bath into the frame.
    Can anyone advise: do I need to make the frame slope for drainage, or is the bath designed to drain when supported by a level frame; do I need to shape the top rail of the frame, or add a packer to support the bath rim at different points? Do I need timber supports under the bath base, or just along the rim? And finally, what kind of glue should I use, how much and where?
    A friend mentioned that plastic baths often creak when you get into them and this is probably caused by slippage of the plastic rim against the frame. Will proper gluing prevent this?
    Thanks

  2. #2
    Join Date
    Apr 2004
    Location
    eastern suburbs, melbourne
    Posts
    486

    Default

    search on google for

    acrylic+bath+frame

    acrylic+bath+frame+glue

    you should find some helpful general info - there is an american site with some very useful pictures.

    I would however be ringing the manufacturer up again and asking for the appropriate information sheet which they almost certainly have. Remember you are legally allowed to install the bath in the frame - its just connecting it to the taps and the drains that you aren't supposed to do.

    As with all baths surrounding the bath with bulk insulation before enclosing it will keep the water hotter longer.
    no-one said on their death bed I wish I spent more time in the office!

  3. #3
    Join Date
    Feb 2005
    Location
    bush
    Posts
    18

    Talking

    i have just recently installed an acrylic bath using 35x70mm timber for the frame.
    as the bath was in the corner of the room i recessed the bath into the wall 25mm so the villaboard and lamipanel would sit in front of the bath lip. this also gives a ready made two side of the bath frame
    the bath should sit level as they are made to drain when installed this way.

  4. #4
    Join Date
    Jul 2002
    Location
    Blacktown, Western Sydney
    Age
    59
    Posts
    76

    Default

    mumu

    I installed an acrylic bath about ten years back and did it just how jackrussel said, even down to the lamipanel. One extra thing I did was sit the bottom of the bath in a fairly sloppy concrete mix so that most of the weight when full was transferred straight to the floor. I can't remember if the instructions that came with the bath said to or whether my dad said to, but I did it.
    and as jackrussel said, build the frame level, the bath has the fall built into it.

    Jon

  5. #5
    Join Date
    Jun 2004
    Location
    Melbourne ,Vic
    Posts
    15

    Default

    Make up the frame as suggested, with a box section around the base on the floor when all is done and you are happy with everything, make up a mortar slurry and pour it in the box.

    Install the bath and fill it with water so that it beds properly..... With a plastic\fibeglass type unit you do need proper support on the bottom, unless it has been designed a special way.....
    Last edited by flat_tyre; 17th February 2005 at 07:02 AM.

  6. #6
    Join Date
    Jul 2004
    Location
    Sale
    Age
    69
    Posts
    559

    Wink

    The bath manufacturer must have an instalation sheet, so definately follow that up. With the mortar bed my understanding is this should be 50mm (2") thick minimum, but silicone should do the job around the bath rim as the base pretty much take the strain, and the framing supports the upper part, you just need to stop the squeek without stressing the bath when it expands and contracts. Goodluck without a sheet its a bit of a pain getting it right.

  7. #7
    Join Date
    Feb 2005
    Location
    Auckland, NZ
    Posts
    4

    Red face Thanks

    Wow
    Thanks a lot everyone, I had not heard of the mortar base trick.
    And I will definitely phone the manufacturer again and press a little harder for information.
    Thanks also for the key-word tips, I'd tried 'bath cradle' but it took me to a lot of sites about babycradles that fit in baths. What next?
    I'll check the sites.
    Would ready-mix concrete or a mortar mix be better if I go this way?

  8. #8
    Join Date
    Jun 2004
    Location
    Melbourne ,Vic
    Posts
    15

    Default

    Mortar would be better, you don't need stones sticking up. If you make a slurry make sure it is not too dry or you will not be able to seat the bath properly....

    You can also line the floor under the bath where your slurry is going with plastic to keep the moisture in... depends on how sealed your floors are or you may end up with mortar floor in your bathroom.... ;-)

  9. #9
    Join Date
    Feb 2005
    Location
    Auckland, NZ
    Posts
    4

    Question recessing into load-bearing wall?

    Thanks for that advice flat-Tyre.
    I must admit I'm a bit wary of mortar on the timber floors, won't it just flow down the hole where the waste pipe goes? Also the technical stuff I have since found on the web suggests these acrylic baths need to sit flat on the floor for structural support, so if I built an edge around the waste to keep the mortar in, I guess it could be no higher than the little support foot built into the base of the bath .
    Now my other main concern is the recess into the wall. My bath is 1675 long, I bought that length because that is the length of the bath that came out.
    The bath fits against one side wall of the bathroom, which happens to be a braced load-bearing wall, and between two end walls. The space from stud to stud of the end walls is just shy of 1675 mm too. Obviously, if I recess the bath in one end, it will fall short at the other end. Also I'm not sure if I can safely cut into the load-bearing side wall.
    The bath I just removed (which was iron) was butted up to the long wall and in the end walls there are bits chiselled out from the studs at the height of the old bath rim, but they are only a couple of mm deep. (This could have been for a previous bath). The walls were lined with old pinex/ softboard, (1930s) A sheet of laminex then went on top of the softboard, down to about 200 mm above the bath and then a timber plank about 300 wide was glued and nailed into the studs all around the wall, covering the gap between the laminex panel and bath, and forming a 'skirting board'. the joint between the plank and laminex was covered by a wooden 1/4 round moulding, and the gap between plank and bath was filled with silicone.
    I now realise the timber plank was probably there to give that additional recess. Would that be right?
    Will I need to do the same? I was intending to butt the bath against the wall, then cover the walls with aqualine gib, cut with a 10 ml clearance above the bath upturn, then cover that with seratone (which has a sealed edge extending 150 mm up the back edge, and bring the seratone down into a pvc moulding that goes between the gib and seratone, and then curves down past the upturn to the bath edge, leaving a gap between it and the gib that gets filled with silicone. (This is all as per seratone's technical instructions, except they show the seratone attached directly to the studs).

    The plumber keeps raising his eyebrows and saying, mouldings are not reliable and the bath should be recessed.
    Any ideas? Should I follow the seratone guide, should i use the plank over the top method, or is it safe to cut into the load-bearing wall (surely not!)
    I might mention, when the bathroom was first built there was probably no shower over the bath, but a shower had been installed probably in the 50s, using the method described above. When I took the panels off the wall, there was no sign of any leakage ever, so they must have done something right.

    thanks for any advice

  10. #10
    Join Date
    Feb 2005
    Location
    bush
    Posts
    18

    Default

    my bath sits on the existing concrete floor but instead of using a stiff mortar mix to bed it in i used a couple cans of expanding foam. the bath being very light had to be weighted down(i just turned the tap on) as the bath was supported on the frame and at the base i felt this was a good alternative.then i packed the surrounding area with pink batts before panelling.
    (plumbers usually know there stuff) cheers rackrussel

  11. #11
    Join Date
    Feb 2005
    Location
    Auckland, NZ
    Posts
    4

    Default

    excellent idea, Rackrussel? Thanks.
    Think I'll either use battens across the wall, to bring the gib out, or use a double gib layer. That should give the same effective inset as a 25 mm cut out of the studs, and improve the sound proofing.
    Cheers
    Mumu

  12. #12
    Join Date
    Jan 2004
    Location
    South of Adelaide
    Posts
    136

    Default

    Under the dozens of acrylic baths I have installed here in SA I have used 2 upended plastic buckets full of reasonably stiff (dry) mortar (brickys sand) placed equidistant along the bottom of the bath, sort of like sand castles. Bed the bath down into this levelling etc. Each 'castle' spreads to the other forming a base along the entire length of the bath. Just mind it doesnt spread along to the outlet and gunk up the thread. Any excess mortar can be cut back with a trowel before it sets. I always use brickys sand because its more fatty (contains clay) and doesnt slump as much as other sands.

    Here in SA we usually have a concrete slab under the bath. The side and end of the bath are let into the walls so the finished wall (tiles etc) covers the raised lip on the bath for water proofing. This is normally sealed with coloured acrylic sealant as a last thing by the tiler. If one end is shy of the wall build a hob out and down to the bath.

    Frame around the skirt of the bath as the others have described or alternatively use hebel block as the norm here.
    Jack

  13. #13
    Join Date
    Aug 2004
    Location
    Melbourne
    Age
    52
    Posts
    121

    Default

    I just installed one last month. Wrapped up the waste with a pink batt, boxed in the bottom of the frame and put in 9 20kg bags of washed sand mixed with 2 2bags of cement.....in a reasonably sloppy mix.

    The end result it the bath has the feel of a cast iron one.

    I glued the bath lip to the frame with Zero Nails, being careful to not get any where the tiles/water proofing went.

    The manufacturer suggested all that was needed is timber battens glued to the bottom of the bath. It did not seem enough for me, thus the cement/sand mix.

    best of luck

  14. #14
    Join Date
    Oct 2003
    Location
    Canberra
    Age
    48
    Posts
    318

    Default

    You should also fill the bath before siliconing the edge to the tiles etc. The water will cause the bath to shift a bit and this will stretch the silicon and weaken it over time.

    Trav

  15. #15
    Join Date
    Jun 2005
    Location
    Melbourne, Australia
    Posts
    1

    Question

    Thanks to all who posted above, your info is very helpful!
    I'm making a timber support frame for an acrylic bath. The rim of the bath is not completely flat underneath, which means the bath will not sit level in the frame.
    I want to be sure everything is ok before I set it into the mortar base!
    What method could I use to ensure the bath sits level?
    Last edited by homeproject; 24th June 2005 at 02:00 PM.