Settling of fill under new garage slab: necessary?
Hi
I want to build a colourbond double garage next to my house. The house was built (40 years ago) on a raised platform of fill. My father suggested I get fill put in next to the house to enable the garage to be level with the house (instead of about 4 feet below). Sounds like a great idea to me. Will I need to wait for the fill to settle before laying the slab? I know there won't be a great deal of weight on it but I'd like to sure before I start proceedings.
Many thanks in advance.
Brett
-
11th November 2007, 05:53 PM #2
Hire a vibrating compacting plate and do the job properly.
Put down a 150mm layer, compact, repeat, repeat, etc, etc.
-
11th November 2007, 06:53 PM #3Senior Member
- Join Date
- Nov 2005
- Location
- Kilsyth
- Age
- 66
- Posts
- 300
about 8 years ago we filled an area, mostly clay fill, to a depth of about 1.2m, over 5 or 6 years it settled down about 150mm, mind you, we did not use a compactor at all, though I did spread it with a bob cat, does that give you an idea.
-
11th November 2007, 11:42 PM #4
If you're going to prepare a platform 1200 high and big enough for a double garage you'll be looking at a lot of fill. Filling to that depth and with that amount of fill you'll need at least a bobcat to spread the fill and a vibrating pedestrian roller to compact. You'll also need to scalp all the topsoil off the site beforehand.
Mick"If you need a machine today and don't buy it,
tomorrow you will have paid for it and not have it."
- Henry Ford 1938
-
12th November 2007, 01:14 PM #5Intermediate Member
- Join Date
- Nov 2007
- Location
- Gunning
- Posts
- 33
thanks
Thanks a lot for your input. I have a much better idea of what's required now. Cheers, Brett
-
12th November 2007, 03:18 PM #6Senior Member
- Join Date
- Feb 2006
- Location
- vic
- Posts
- 174
It would probably crack with normal reo with no internal beams if you drive a car on it.
-
12th November 2007, 07:06 PM #7Senior Member
- Join Date
- Jul 2004
- Location
- Singleton NSW
- Age
- 69
- Posts
- 33
I filled an area to about 900mm for my 6M X 14M shed. It has sunk about 50 - 70 mm in a couple of places - Unfortunately a family of Red Belly Black Snakes have now moved into the gap
woodcutta
-
12th November 2007, 08:16 PM #8Senior Member
- Join Date
- Nov 2005
- Location
- Kilsyth
- Age
- 66
- Posts
- 300
filled areas have a bad habit of doing that, even if you roller compact as you go.
Unfortunately a family of Red Belly Black Snakes have now moved into the gap
woodcutta
-
12th November 2007, 09:06 PM #9
What you could do is put your fill in and compact as well as possible, then get a machine in to drill some holes into solid ground beneath the fill area, then fill with concrete to act as piers to hold up your slab.
-
14th November 2007, 01:29 PM #10Senior Member
- Join Date
- Jul 2004
- Location
- Singleton NSW
- Age
- 69
- Posts
- 33
[quote=
look on the bright side..... ummmm, can't think of one at the moment, but 'always look on the bright side of lie, da dum, da dum dum dum dum'[/quote]
Maybe they sleep in the winter??
woodcutta
-
14th November 2007, 01:34 PM #11
One part of our house sits on an infill slab. It has brick piers every metre with extra reo over the piers (as specified by the engineer). It is back filled with sand, which does not compress - however it only needs to act as formwork for the slab pour because the piers will take the weight. The piers are founded in solid ground with a 600x600x600 footing under each. The perimeter of the slab sits on continuous brickwork which is laid on a strip footing. There is a slip joint between the slab and the brickwork.
"I don't practice what I preach because I'm not the kind of person I'm preaching to."
-
14th November 2007, 07:56 PM #12
4 foot is a decent depth to fill, Brett. Not something I'd take too lightly. The idea of dumping fill in there and compacting it doesn't work for me. It will settle over time and cause problems.
In fact, I don't think I'd tackle it myself because it sounds like it needs:
* Something to retain the fill, i.e, retaining walls
* Piers into solid ground
* Crusher dust or sand (non-compacting fill)
* Then the slab (that sits on the piers.
But most of all, you need a soil test and an engineer. I'd be very surprised if the council will let you do anything other than have an engineer look at it if you want to raise it four feet. Silent's post outlines the way it needs to be done.
-
17th November 2007, 08:13 AM #13Intermediate Member
- Join Date
- Nov 2007
- Location
- Gunning
- Posts
- 33
Thanks for all the advice. I knew what to expect when I called the garage people who put me on to the concreter. He said it wouldn't be a drama - he'd put piles down to hard ground and lay the slab on top. No big deal (it would cost a bit more of course, but that was to be expected). He did make the good suggestion that I step the garage down, ie only half the fill-height, so the buildings flowed more with the block. Sound idea. Thanks again everyone. It's amazing how quickly you can go from knowing absolutely nothing to having a bit of an idea.
cheers, Brett
Similar Threads
-
Estimate cost of garage slab please?
By juliussee in forum CONCRETINGReplies: 21Last Post: 17th March 2008, 06:35 PM -
Advice Needed: Hefty Retaining Wall + Garage (Photos)
By RedRaven in forum LANDSCAPING, GARDENING, OUTDOORSReplies: 4Last Post: 13th October 2007, 08:59 AM -
garage slab engineering
By Amb in forum CONCRETINGReplies: 7Last Post: 23rd July 2007, 12:12 PM -
garage slab concrete - subbase
By XT4V in forum CONCRETINGReplies: 34Last Post: 1st May 2006, 07:39 AM
Bookmarks