    I'm extend my front porch out about 1.8m. The existing porch is just a tad over 3m wide and I'm wondering if/how to connect the existing slab to the new one.
    I had thought of drilling horiz holes in the end of the existing slab and poking some reo in there or putting in some long dyna bolts and leaving them stick a 100mm or maybe some chemset bolts. Just to tye it ot the new slab. Not sure if I need to do this or if I;m on the right track.
    Anyone have any ides?

    Cheers

  2. #2
    Join Date
    Oct 2003
    Location
    Gold Coast
    Posts
    8

    Default

    It depends on what is going to be sitting on your slab... Are you extending out your veranda or patio roof? Is your house brick veneer or timber clad?

    If you move the veranda posts out to the new slab to extend your roof, you'll have to think about the possibility of the two slabs sinking or rising at different rates unless the underslab compaction is exactly the same. Timber and steel frames can flex a bit, masonry doesn't flex. So if you intend having a structure that is connected to two different slabs, you want to be pretty sure that the two slabs are not going to move at different rates and cause excessive flexing of the structure.

    For a structural slab, I think Rebar chem-set into horizontal holes in the existing slab is the way to go, but I'm not a qualified strucutral engineer...
    "If something is really worth doing, it is worth doing badly." - GK Chesterton

  3. #3
    Join Date
    Jun 2007
    Location
    sydney
    Posts
    121

    Default

    The house is brick veneer and I will be putting a timber deck over both slabs.

    Just running battens and then some 90x19 Merbau decking

  4. #4
    Join Date
    Aug 2006
    Location
    Sydney
    Age
    65
    Posts
    1,248

    Default

    If you're running a deck over why waste the money? Is it a height issue with the door threshold?

    Even if thats the case wouldn't it be the same amount of trouble to Dyna bolt a bearer plate to the front of the slab and run joists ontop to the same height of the battens?

  5. #5
    Join Date
    Oct 2006
    Location
    Tallahassee FL USA
    Age
    82
    Posts
    0

    Default

    1.8m is a substantial cantilever for any size joists. Without knowing the properties of the existing slab, it's hard to tell whether flexural continuity can be achieved. I'd guess the best function of the slab extension would be to provide a foundation for the battens and protect them from ground contact. Tying slabs together to avoid vertical misalignment is best done with reo for the new slab embedded about 200mm into epoxy-filled holes in the existing slab. A crack will likely develop along the top of the interface; to prevent corrosion of the reo, form a slot about 12mm x 12mm along the top edge of the new slab at the junction, thoroughly clean all surfaces of the slot, and fill with a flexible sealant such as silicone or polyurethane.

    Joe
    Of course truth is stranger than fiction.
    Fiction has to make sense. - Mark Twain

  6. #6
    Join Date
    Jun 2007
    Location
    sydney
    Posts
    121

    Default

    Thanks Joe,
    I'll get myself some reo today and start drilling.

    I originally planned to quickset a few stirups into the ground and put some bearers in but trying to get 3 to line up level with the existing slab I thought might be too hard so I decided to just put a slab down. That way i can just get the formwork all level and screed the concrete to suit.

  7. #7
    Join Date
    Oct 2006
    Location
    Tallahassee FL USA
    Age
    82
    Posts
    0

    Default

    G'day, Tubby.
    If the existing slab slopes outward, just follow that slope with the new slab. If the old slab is level, set the outer edge about 25mm lower to assure drainage; You can shim the battens there to make everything level. Shim spacing can be about 4 times the depth of the battens.

    Joe
    Of course truth is stranger than fiction.
    Fiction has to make sense. - Mark Twain

  8. #8
    Join Date
    Jun 2007
    Location
    sydney
    Posts
    121

    Default

    All done. Thanks for the help guys, Now I'm just going to wait a week before I start fixing battens to it.
    Screeding concrete is a bastard of a job. I'm glad I did a small section first as I was going to do some more out the back at the same time. Lucky I didnt.

    Thanks again

Similar Threads

  1. extending brickwork
    By scottyb in forum BRICKWORK
    Replies: 4
    Last Post: 20th August 2007, 10:12 PM
  2. deck with no clearance over concrete slab
    By gsouth in forum DECKING
    Replies: 7
    Last Post: 17th March 2007, 05:50 PM
  3. Extending a concrete slab
    By princhester in forum CONCRETING
    Replies: 8
    Last Post: 24th July 2005, 08:49 PM

Tags for this Thread

Bookmarks

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •