    Default stepped footings

    Hi,
    Can anyone offer any advice on how to do stepped footings? We have our trenches dug to the right depth and are gonna construct some formwork where necessary. But our conundrum is how to stop the concrete from just flowing downhill and therefore overflowing at the lowest point. do we need to order thick mix. By the time we reach the top we have risen by 3 mteres..
    or do we have to pour the individual steps separately? and wait for them to go off?
    Cheers

  2. #2
    Join Date
    Aug 2003
    Location
    Pambula
    Age
    59
    Posts
    5,026

    Default

    If the concrete runs out the bottom it's too wet - send it back!

    No expert on it, but I guess our strip footings varied in height by about the same amount as yours and we poured them all on the same day. The combination of the stiffness of the mix plus the reo should hold it up. Well, it did on ours, anyway.

  3. #3
    Join Date
    Nov 2003
    Location
    Australia and France
    Posts
    2,869

    Default

    Oh dear!

    3 metres is a lot of metres!

    Concrete isn't that fluid, if your formwork is strong enough you'll be OK, although if you are really concerned you can order stuff with a lower slump.

    DON'T add water!


    Cheers,

    P

  4. #4
    Join Date
    Feb 2006
    Location
    Byron Bay
    Posts
    0

    Default

    Thanks
    I'm no expert on it too.. So you had steps too.. did you just put a block at the start of each rise to create the vertical face of the step?
    cheers

  5. #5
    Join Date
    Aug 2003
    Location
    Pambula
    Age
    59
    Posts
    5,026

    Default

    For the 1 or 2 course steps, we just had height pegs and finished the face with the trowel. For the big drops, a bit of form ply against a couple of stakes either side of the trench for the face. You can get fancy and box it in but ours was mostly contained on the sides by the trench. None of ours is visible (or the few bits that are visible now wont be for long) so we didn't bother getting fussy with it.

Similar Threads

  1. Footings to set?
    By Spelunx in forum FLOORING, DECKING, STUMPS, etc.
    Replies: 10
    Last Post: 16th March 2007, 07:45 PM
  2. Do strip footings need plastic underneath?
    By meo in forum CONCRETING
    Replies: 2
    Last Post: 2nd June 2006, 10:29 PM
  3. Concrete Footings...Is there a better way?
    By Flyboy in forum CONCRETING
    Replies: 38
    Last Post: 4th September 2005, 06:19 PM
  4. Footings for parpet wall - help please
    By Interwood in forum CONCRETING
    Replies: 5
    Last Post: 6th April 2005, 07:35 PM

Tags for this Thread

Bookmarks

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •