Thread: Waterproofing Ensuite
-
4th February 2007, 05:38 PM #1Member
- Join Date
- Nov 2005
- Location
- Brissy
- Posts
- 54
Waterproofing Ensuite
Hi Folks,
Need some quick help regarding waterproofing the ensuite as part of an extension. I have AS3740, AS4858 and the Building Code however it isn’t as clear as I would have hoped.<O</O
<O</O
At this stage I have 16mm fibre cement sheeting on Joists for the floor and 6mm Villaboard for all the walls. The shower will be frameless so I will waterproof the whole floor and the whole area (walls and floors) will be tiled. I haven’t jointed the sheets etc. yet thus my questions are:<O</O
<O</O
Should I joint the sheet joins (wall/wall and wall/floor) with paper tape and 2 coats base coat? What about the nails?<O</O
What to use around the wall/floor joins prior to putting down the waterproof membrane? (flashing, silicone etc)<O</O
What to use for the waterproof membrane?<O</O
What to use for a waterstop at the door? (can you just use tile trim and then waterproof up to the top as part of the main membrane).<O</O
<O</O
I need to bed first before tiling to get the falls to the shower and floor waste so can a sealant be added to this and this form the main membrane? Should the membrane go under the bed or over it?<O</O
<O</O
I will go 150mm around the walls and 1800mm in the area that the shower is. <O</O<O</O
Anyone think of anything else I need to know?<O</O
<O</O
Thanks in advance<O</O
-
4th February 2007, 06:11 PM #2New Member
- Join Date
- Dec 2006
- Location
- Sydney
- Posts
- 9
Hi,
When i did my bathroom, for the wall joints I put paper tape & 2 coats of base coat and did nail heads as thought was going to tile so far then paint. I waterproofer to to waterproofing, they put fiberglass matting down and coated with membrane and a bead was placed on floor around shower and coated with membrane to keep water in shower floor area and one bead was put in doorway. Shower walls were coated to height of shower screens. All the floor plumbing around floor wastes etc should be fitted and coated with membrane also. Then fitting can be fitted for tiling. My floor tiles were then fixed with a sand & cement mix and a tile adhesive for the walls. Hope this helps a little.
-
4th February 2007, 06:45 PM #3
-
5th February 2007, 09:32 PM #4Member
- Join Date
- Nov 2005
- Location
- Brissy
- Posts
- 54
Looks like I have to go with a pro as my certifier tells me that I need a certificate from a Licensed waterproofer in order to pass final inspections (Brisbane based)
Thanks Mark and Mic for responding – appreciate your help<O</O
-
6th February 2007, 11:33 AM #5Member
- Join Date
- Nov 2005
- Location
- Brissy
- Posts
- 54
OK need some more help
Waterproofer is suggesting 40mm trims at door and shower area to allow for fall etc. however 40mm seems huge. I note mic-d that in a response back in 05 you comment about doing 3 hobless showers and also used 40mm trim and mortared the whole room etc. so what happens with the raised floor level? My concern was (refer pic) I have 19mm hardwood flooring in the bedroom and 16mm Fibre Cement Sheeting as flooring in the ensuite so if I have 40mm at the door (and mortar/tile to that level) the bathroom floor is significantly higher than the bedroom floor level. Anyone care to comment or share experiences (is that normal for example?). <O</O
<O</O
The ensuite is only 1.7 x 1.8 and the shower is 900x900 cornered so could I get away with say a 25mm angle which is allowing 15mm bed at it highest point (can I taper it down to nothing at wastes?) and 10mm for tile/adhesive?<O</O
<O</O
If I had thought about it prior to installing all the wall sheeting etc. I would have just checked the floor sheeting 20-25mm into the joists but if I did that now I would have a 20-25mm gap at the bottom. But saying that I assume in most instances the floor levels are normally level for joist type construction so what’s the norm with differing floor levels in rooms?<O</O
<O</O
TIA<O</O
-
6th February 2007, 12:40 PM #6SENIOR MEMBER
- Join Date
- Apr 2005
- Location
- Sydney
- Age
- 64
- Posts
- 882
Yes, It's quite common to have a step up to a bathroom. It's also quite common to set bathroom floor joists at a lower level (40mm or so) to compensate for the tile bed, fall, and tile thickness, which would then give a flush finish between finished floor levels. It's a bit of a pain in the bum, because you have to set down all the joists between two bearers, and pack up the parts of the floor outside the bathroom. If you wanted to rip down the parts inside the bathroom, you'd have to ensure they could span the distance with their finished depth.
With a small ensuite, you can just plane to joists with a slight fall to a corner floor waste, then just glue the tiles straight down to the membrane.
It's also quite common to install plastic angles glued down to the flooring around the perimeter and up the corners of a bathroom, before you install the wall sheets. This gives extra waterproofing protection, but obviously it's too late for this in your case.
I believe that you shouldn't go less than 20mm thick (at the thinnest point) with the cement bed under tiles. If you put a hob around your shower, then you could put a fall in your shower, and just glue the rest of the tiles straight to the membrane without any fall. Just put a slight fall (built up with glue) to the angle at the doorway. Of course it's not the best if you're in the habit of spilling a lot of water on your floor, or if you want to mop it by pouring water all over it, or if you get a leak in one of your fixtures, (eg cistern) but it will give you less difference between floor levels.Last edited by pawnhead; 6th February 2007 at 01:34 PM. Reason: More information added
-
6th February 2007, 06:57 PM #7
20-25mm is the minimum you should be thickness you should be going for. 40mm is common and looks OK. You can hide the step behind a timber wedge or tiles if you like.
Cheers
Michael
-
7th February 2007, 10:35 PM #8
To work out your levels you need to know the greatest distance from your floor traps to the furthest wall.
Eg measure from the floortrap to the wall furthest from it. You need to start prefferably 15-20 mm thick and add at the very least 15 mm per meter fall to the floor, preferably more eg 20-30.
Easiest way to do...
mark a 600 level at 500 mm put a wood chock 5-10mm thick at this point, tape it to your straight edge so that when the level is level the straight edge is at the correct fall for screeding.If you dont play it, it's not an instrument!
-
8th February 2007, 08:50 PM #9Intermediate Member
- Join Date
- Jul 2006
- Location
- Brisbane
- Posts
- 39
I agree with all on the 40mm step up - it's fine. I'm almost finished a bathroom where there is a 40mm step up from the existing timber floor. I was worried about tripping and have had no problems.
You'll need a significant fall in the shower if you're going frameless. Or you'll need a small strip that sits on the tiles to help keep the water in.
-
11th February 2007, 04:27 PM #10
Similar Threads
-
Waterproofing regulations in Victoria
By cookiecrumbs in forum KITCHENS, BATHROOMS, THEATRES, etcReplies: 0Last Post: 20th November 2006, 05:15 PM -
Waterproofing the bathroom - help!
By Lonks in forum KITCHENS, BATHROOMS, THEATRES, etcReplies: 5Last Post: 9th March 2006, 09:48 PM -
Waterproofing a ensuite
By John99 in forum PLUMBING, ELECTRICAL, HEATING, COOLING, etcReplies: 11Last Post: 10th January 2006, 09:46 PM -
Waterproofing
By Flyboy in forum KITCHENS, BATHROOMS, THEATRES, etcReplies: 1Last Post: 6th January 2006, 01:31 PM -
Waterproofing and bath installation
By Hybrid in forum PLUMBING, ELECTRICAL, HEATING, COOLING, etcReplies: 10Last Post: 18th July 2005, 12:25 AM