Hi Guys;

Below is some pics of a semi major reno we have just completed for a client, it was done in two stages, the front of the house was converted to new bedrooms / en suite enclose veranda's, all new Sydney Bluegum Flooring etc, while the occupants lived in the rear of the house, then we moved them into the front part and ripped the back of the house apart.

Back part consisted of destruction of 6 rooms inc Laundry, Kitchen, old garage which was being used as a bedroom, house was double brick construction,all 6 rooms had to go an be converted in to one huge room, new bi folds and new pergola, What are your thoughts on the results

Original Plans


Proposed Changes



Starting to put some new walls and level out the terrazo veranda to become future bedrooms




Ripping out of the old kitchen


Starting to demolish old lounge room


Propping the ceiling and purlins allowing removal of multiple walls


Removal of old back windows to make way for Bi Fold Doors


New steel beams ready to go up, 3 in total


Steel Up


New ceiling all levelled off


Starting to take up all the old floors


New floors down secret nailed, bi folds in



Starting new pergola