? does fix price quote include unforseens
Hi All (particularly the builders amongst us)
I am doing a 100m2 extension over 2 storeys.
In integrating the extension back into the house we found a massive amount of termite damage and have had to replace every internall wall on the ground floor. Also have had to put in 2 structural steel beams and replace a fair few 300mm floor joinst between the floors.
I am just wondering with all the discussions about cost and OB doing work wether if abuilder had been involved all these extra costs would have been on top of the already steep prices discussed on various posts or is the steep cost just incase of this sort of problem being encountered?
We leveled the house as we built the new load bearing walls. This is now some months ago I now find that the upper story has settled again.
Drawing on the forum collective wisdom is this settlement likely to be due to shrinkage in the wood I used (oregon) or could there be some other reason that I have overlooked. As a lead up to this job we jacked up and underpinned the house where required down to rock and all the new steel structural beams have been projected back through to the foundation.
Cheers