Renovations from start to finish Part A
For no real reason I have decided to start tracking our renovations on the forum, from start to finish. I have been posting pits and pieces of our internal work, but I figure I can get heaps of good advice if I start posting info about the work we are undertaking outside. I'll add photos as we go.
Getting up to speed. We are currently getting quotes from builders for the complete job, however we have decided in the last few days to do it as owner builders. Originally we were going to go with a fixed price contract because which bank wouldn't lend money to owner builders, however we have since found that we are getting very high quotes from the builders and have figured out that there are other banks around. We are using a mortgage broker who is chasing up banks who will lend what we need to owner builders.
The process so far. We spent some 12 months looking at options regarding purchasing a new house, demolishing this one, adding on etc. I think we had around 15 or 16 different options. In the end we have settled on adding on because we got the house at such a good price $88,000 and 2 years later it (as is) it is probably worth around $200,000. Now, we figure that including added value of the addition, we could theortically spend around $200,000 and not over capitalise. However we want to avoid the trap of spending the money that we are capable of spending and only spend what we have to. There are also of course a myriad of life style choices which come with this house as well.
Once we decided on the addition, we then looked at what to do - go up, go sideways or go back. We decided on building over our driveway( sideways), because the drive runs the length of the house, is relatively useless space, we have rear lane access and we can design the house to match the existing.
With our layout already in mind we went to a draftee who took about a week or so (very quick) to come up with plans which we then took to the council.
To be continued.............
Electricity into the house Part E
This bit didn't start off as part of the addition but it has sort of worked it's way in.
Originally we were going to leave our electricity where it is coming into the house on the North side (to the right in the piccies), however the box is very old and our sparkie has suggested we renew it. He also originally suggested we move the box to wall on the new addition (the South side) because Country Energy (the local authority) will require us to move the incoming wire as it currently crosses the neighbours property (this is a big no no). And whilst they are happy with the status quo, Country Energy has said that they will require us to move it as part of any renovations.
So everything was going along swimmingly until the sparkie realised that the distance between the boundary and the wall on the new bit was only 600mm. Which means it would be illegal to place a box there. Given that the door on the box has a 600mm swing and that should something explode there, a person has nowhere to back away to!! Therefore we are now replacing the switch box in it's existing position, but to sidestep the power over the neighbour we are putting up a 3 metre high pole (+1200 into the ground!) at the front of our house and running the power underground to the switch box. This means once I finish typing this and a little plastering I have I will be back into hand trenching a 600mm deep trench from the house to the pole (about 4m). I am hand trenching cause it's not that far and also I am very near our water mains and Telstra cable (gas mains is on the other side of the house thankfully)
Between the cost of the pole, new switch box, sparkies time, Country Energy fee and bits and pieces, this costs around $1400
To be continued............