PDA

View Full Version : Stormwater line and deck footings















Reno RSS Feed
22nd November 2008, 05:20 PM
Hi all,

Not sure which catagory this should go into. I'm digging my footings for a 2nd floor deck. 500mmx500mm by 800mm deep as per engineers drawings.

However I've hit the stormwater drain and sewer drain at 600mm. The stormwater is almost through the middle, the sewer just off to the side, see drawings.

What's the best way of working around this problem?

Thanks!
Jeremy

Attached Thumbnails http://www.renovateforum.com/attachment.php?attachmentid=74466&stc=1&thumb=1&d=1227331748 (http://www.renovateforum.com/attachment.php?attachmentid=74466&d=1227331748)



Read the full thread at RenovateForum.com... (http://www.renovateforum.com/showthread.php?t=74592&goto=newpost)